b) A senior accountant has four juniors working under her as trainees, and four tasks to be executed. The juniors differ in efficiency and the tasks differ in their intrinsic difficulty.
Her estimate of the time in minutes each junior would take to perform each task, is tabulated below
JUNIORS
TASKS |
MsA |
MsB |
MsC |
MsD |
T1 |
10 |
17 |
25 |
16 |
T2 |
25 |
12 |
27 |
13 |
T3 |
14 |
37 |
18 |
17 |
T4 |
9 |
18 |
25 |
23 |
How should the tasks be allocated, one to each junior, so as to minimize the total work-time (minutes)?
b) A senior accountant has four juniors working under her as trainees, and four tasks to be executed. The juniors differ in efficiency and the tasks differ in their intrinsic difficulty. Her estimate of the time in minutes each junior would take to perform each task, is tabulated below JUNIORS TASKS MsA MsB MsC MsD T1 10 17 25 16 T2 25 12 27 13 T3 14 37 18 17 T4 9 18 25 23 How should the tasks be allocated, one to each junior, so as to minimize the total work-time (minutes)?
Attachments:
Needs help with similar assignment?
We are available 24x7 to deliver the best services and assignment ready within 3-4 hours? Order a custom-written, plagiarism-free paper